9
LANDSCAPE AND VISUAL IMPACT ASSESSMENT
9.1
Introduction
9.1.1.1
This section presents the methodology for the assessment
of the potential landscape and visual impact associated with the construction
and operational phases of the Project. The proposed works include the
construction and operation of (i) a sludge treatment
facility located in the East Ash Lagoon area, and (ii) an access roadworks to connect the facility to the existing Nim Wan Road.
9.1.1.2
This landscape and visual impact assessment (LVIA)
follows the criteria and guidelines as stipulated in Annexes 10 and 18 of
Environmental Impact Assessment Ordinance (EIAO) Technical Memorandum and EIAO
Guidance Note No. 8/2002.
9.1.1.3
The photomontages and general layouts provided in this
report are based on the reference design. The actual design will be
carried out by the contractor. It should be noted that the reference
design will be used by the contractor for reference, but will not constrain the
actual design.
9.2
Project Description
9.2.1.1
Figure 9.1 shows a location plan for the project and Figure 9.2 shows the aerial view of
the existing ash-lagoon and the surrounding areas in Nim
Wan. Full description and justification on the need on the extension project is
provided in Section 2 of this report.
9.3
Environmental
Legislation and Standards
9.3.1.1
The following have been considered:
·
Environmental Impact Assessment Ordinance, Annexes 10
and 18 of Environmental Impact Assessment Ordinance (EIAO) Technical Memorandum
and EIAO Guidance Note No. 8/2002.
·
The Forests and Countryside Ordinance (Cap96) –
prohibits felling, cutting, burning or destroying of trees and growing plants
in forests and plantations on government land. Its subsidiary regulations prohibit
the picking, felling or possession of listed rare and protected plant species.
·
The Forestry Regulations – made under Section 3 of the
Forests and Countryside Ordinance (Cap. 96), defined
the list of protected species in Hong Kong.
·
Protection of Endangered Species of Animals and Plants
Ordinance (Cap 586);
·
Government General Regulation 740 – sets out
restrictions on the preservation and felling of trees in Hong
Kong.
·
ETWB TC(W) No. 29/2004
Registration of Old and Valuable Trees and Guidelines for their Preservation –
provides priority protection to the trees in the Register. Furthermore,
the Government has already put in place a comprehensive range of administrative
and legislative measures to preserve trees on Government land.
·
ETWB TC(W) No. 2/2004
Maintenance of Vegetation and Hard Landscape Features – sets out the government
departmental responsibilities for maintenance of vegetation and hard landscape
features.
·
ETWB TCW No. 3/2006 - Tree Preservation
·
ETWB TCW No. 11/2004 - Cyber Manual for Greening
·
WBTC No. 14/2002 Management and Maintenance of Natural
Vegetation and Landscape Works, and Tree Preservation – defines and outlines
the management and maintenance responsibilities for natural vegetation and
landscape works, and the authorities for tree preservation and felling.
·
WBTC No. 7/2002 Tree planting in Public Works – affirms
the advocated policy on tree planting which adopts a flexible and balanced
approach in the planning and design of public works.
·
WBTC 17/2000 – Improvement to appearance of slopes,
outlines the principles and procedures recommended for all departments involved
in new slope works and maintenance of existing slopes for improving aesthetic
and environmental impact of slope works.
·
WBTC No. 25/93 – Control of Visual Impact of slopes,
outlines the design principles recommended to be used in designing man-made
slopes for Public Works projects in order to reduce their adverse visual
impact.
·
GEO publication No. 1/2000 - ‘Technical Guidelines on
Landscape Treatment and Bio-engineering for Man-Made Slopes and Retaining
Walls’.
·
Technical Report of Landscape Value Mapping in Hong
Kong by Planning Department – establishes the essential landscape baseline
information which provides a systematic reference framework to facilitate
landscape assessment and broad environmental assessment of major projects at
territorial level.
·
Government General Regulation 740 – restrictions on the
preservation and felling of trees in Hong Kong
·
Hong Kong Planning Standards and Guidelines Chapter 4 and Chapter 11
·
Study on Landscape Value Mapping of Hong
Kong
9.4
Methodology of Assessment of Landscape Impacts
9.4.1
Introduction
9.4.1.1
Landscape and visual impacts have been assessed separately
for the construction and operation phases.
9.4.1.2
The assessment of landscape impacts has involved the
following procedures:
9.4.2
Identification of Baseline Landscape Resources
9.4.2.1
Site visits and desktop study of topographical maps,
information databases and photographs were carried out to identify the baseline
landscape resources within the sites and works area.
9.4.3
Assessment of Degree of Sensitivity to Change
9.4.3.1
The degree of sensitivity to change of the landscape
resources would be influenced by a number of factors including:
·
quality and maturity of landscape resources/characters,
·
rarity
of landscape resources/characters,
·
whether is considered to be of local, regional, national or global
importance,
·
whether there are any statutory or regulatory limitations/requirements
relating to the landscape resource/characters, and
·
ability of the landscape resource/character to accommodate change.
9.4.3.2
The sensitivity of each landscape resources and
character areas is classified as follows:
High:
|
Important landscape
or landscape resources of particularly distinctive character or high
importance, sensitive to relatively small changes.
|
Medium
|
Landscape or
landscape resources of moderately valued landscape characteristics reasonably
tolerant to change.
|
Low:
|
Landscape or
landscape resources of low valued landscape characteristics.
|
9.4.4
Identification of Potential Sources of Landscape
Impacts
9.4.4.1
The elements of the construction works and operational
procedures that would generate landscape impacts are identified.
9.4.5
Identification of Magnitude of Landscape Impacts
9.4.5.1
The magnitude of the impact (or magnitude of
change) depends on a number of factors including:
·
the
physical extent of the impact,
·
compatibility of the project with the surrounding landscape,
·
duration of impacts i.e. whether it is temporary (short, medium or long
term), under construction and operation phases, and
·
reversibility of change.
9.4.5.2
The magnitude of landscape impacts is classified as
follows:
Large:
|
The landscape or landscape resource would
suffer a major change.
|
Intermediate:
|
The landscape or landscape resources
would suffer moderate change.
|
Small:
|
The landscape or landscape resources
would suffer slight or barely perceptible change.
|
Negligible:
|
The landscape or landscape resources
would suffer no discernible change.
|
9.4.6
Identification of Potential Landscape Mitigation
Measures
9.4.6.1
Mitigation measures may take the form of:
·
adopting alternative design or revisions to the basic
engineering and architectural design to prevent and/or minimize adverse
impacts,
·
remedial measures such as colour and textural
treatment of physical, engineering and building features, and
·
compensatory measures such as implementation of landscape design measures (e.g.
tree planting, creation of new open space etc) to compensate for unavoidable
adverse impacts and to attempt to generate potentially beneficial long term
impacts.
9.4.6.2
The agencies responsible for the funding
implementation, management and maintenance of the mitigation measures are
identified.
9.4.7
Predicted Significance of Landscape Impacts
9.4.7.1
By synthesising the magnitude
of various impacts and the sensitivity of various landscape resources it is
possible to categories impacts in a logical, well-reasoned and consistent
fashion. Table 9.1 shows the rationale for dividing the degree of
significance into four thresholds, namely insubstantial, slight, moderate, and
substantial, depending on the combination of a
negligible-small-intermediate-large magnitude of impact and a low-medium-high
degree of sensitivity of landscape resource/character.
Table 9.1
Relationship between Receptor Sensitivity and Impact Magnitude in Defining
Impact Significance
|
Receptor Sensitivity (of Landscape Resource,
Landscape Character Area or VSRs)
|
Low
|
Medium
|
High
|
Magnitude of Impact (Change)
|
Large
|
Moderate
|
Moderate
/ Substantial
|
Substantial
|
Intermediate
|
Slight
/ Moderate
|
Moderate
|
Moderate / Substantial
|
Small
|
Insubstantial
/ Slight
|
Slight
/ Moderate
|
Moderate
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
9.4.7.2
The significance of landscape impacts before and after
implementation of mitigation measures are predicted.
9.4.8
Prediction of Acceptability of Impacts
9.4.8.1
An overall assessment of the acceptability, or otherwise,
of the impacts according to the five criteria set out in Annex 10 of the
EIAO-TM.
9.5
Methodology of Assessment of Visual Impacts
9.5.1
Introduction
9.5.1.1
The assessment of visual impacts has involved the
followings.
9.5.2
Identification of Zones of Visual Influence (ZVIs)
9.5.2.1
Site visits and desktop study of topographic maps and
photographs, and preparation of cross-section are carried out to determine
visibility of the project during the construction and operation phase from
various locations and to identify the zones of Visual Influence (ZVIs).
9.5.3
Identification of Visual Sensitive Receivers (VSRs)
9.5.3.1
Visual Sensitive Receivers (VSRs)
are the people who would reside within, work within, play within, or travel
through, the ZVIs during the construction and
operation stages.
9.5.4
Assessment of Degree of Sensitivity to Change
9.5.4.1
In the assessment of the degree of sensitivity to
change of the VSRs, the types of VSRs
are considered. Those VSRs who view the impact from
their homes are considered to be highly sensitive as the attractiveness or
otherwise of the outlook from their home would have a substantial effect on
their perception of the quality and acceptability of their home environment and
their general quality of life. Those who view the impact from their workplace
and at school are considered to be only moderately sensitive as the
attractiveness or otherwise of the outlook would have a less important,
although still material, effect on their perception of their quality of life.
The degree to which this applies depends on whether the workplace is
industrial, retail or commercial. Those who view the impact whilst taking part
in an outdoor leisure activity may display varying sensitivity depending on the
type of leisure activity. Those who view the impact whilst traveling on a
public thoroughfare would also display varying sensitivity depending on the
speed of travel.
9.5.4.2
Other factors which are considered (as required by EIAO
GN 8/2002) include the value and quality of existing views, the availability
and amenity of alternative views, the duration or frequency of view, and the
degree of visibility.
9.5.4.3
The sensitivity of VSRs is
classified as follows:
High:
|
The VSR is
highly sensitive to any change in their viewing experience.
|
Medium:
|
The VSR is
moderately sensitive to any change in their viewing experience.
|
Low:
|
The VSR is
only slightly sensitive to any change in their viewing experience.
|
·
9.5.5
Identification of Relative Numbers of VSRs
9.5.5.1
The relative numbers of VSRs
is expressed in term of whether there are very few, few, many or very many VSRs in any one category of VSR.
9.5.6
Identification of Potential Sources of Visual Impacts
9.5.6.1
The elements of the construction works and operational
procedures that would generate landscape impacts are identified.
9.5.7
Assessment of Potential Magnitude of Visual Impacts
9.5.7.1
In the assessment of the potential magnitude of visual
impacts, the following factors are considered:
·
the compatibility with the surrounding landscape
·
the duration of the impact
·
the reversibility of the impact
·
the scale of the impact and distance of the source of
impact from the viewer
·
the degree of visibility of the impact, and the degree
of which the impact dominates the field of vision of the viewer
9.5.7.2
The magnitude of visual impacts is classified as
follows:
Large:
|
The VSRs would suffer a major change in their viewing
experience.
|
Intermediate:
|
The VSRs would
suffer a moderate in their viewing experience.
|
Small:
|
The VSRs would
suffer a small change in their viewing experience.
|
Negligible:
|
The VSRs would
suffer no discernible change in their viewing experience.
|
9.5.8
Identification of Potential Visual Mitigation Measures
9.5.8.1
These may take the form of adopting alternative
designs or revisions to the basic engineering and architectural design to
prevent and/or minimise adverse impacts, remedial
measures such as colour and textural treatment of
building features, and tree planting to screen the roads and associated bridge
structures. A programme for the mitigation measures
is provided. The agencies responsible for the implementation, management and
maintenance of the mitigation measures are identified and their
approval-in-principle has been sought.
9.5.9
Prediction of Significance of Visual Impacts
9.5.9.1
By synthesising the magnitude
of the various visual impacts and the sensitivity of the VSRs,
and the numbers of VSRs that are affected, it is
possible to categorise the degree of significance of
the impacts in a logical, well-reasoned and consistent fashion. Depending on
the combination of a negligible-small-intermediate-large magnitude of impact
and a low-medium-high degree of sensitivity of VSRs,
the rationale for dividing the degree of significance into four thresholds is
shown below, including insubstantial, slight, moderate and substantial,
9.5.9.2
The significance of visual impacts is categorized as
follows:
Substantial:
|
Adverse /
beneficial impact where the proposal would cause significant deterioration or
improvement in existing visual quality.
|
Moderate:
|
Adverse / beneficial
impact where the proposal would cause a noticeable deterioration or
improvement in existing visual quality.
|
Slight:
|
Adverse /
beneficial impact where the proposal would cause a barely perceptible
deterioration or improvement in existing visual quality.
|
Insubstantial:
|
No
discernible change in the existing visual quality.
|
9.5.9.3
The significance of landscape impacts before and after
implementation of mitigation measures are predicted.
9.5.10
Prediction of Acceptability of Impacts
9.5.10.1
An overall assessment of the acceptability, or
otherwise, of the impacts according to the five criteria set out in Annex 10 of
the EIAO-TM.
9.5.10.2
Funding, implementation, management and maintenance of
the mitigation proposals can be satisfactorily resolved according to the
principles in ETWB TCW No. 3/2006. All mitigation proposals in this report are
practical and achievable within the known parameters of funding, implementation,
management and maintenance. Approval-in-principle to the implementation,
management and maintenance of the proposed mitigation measures is being sought
from the appropriate authorities.
9.6
Baseline Study
9.6.1.1
Landscape baseline review comprises of the
identification of all existing Landscape Resources (LR) and Landscape Character
Areas (LCA) within 500m from the project. They are mapped in Figure 9.3 and Figure 9.8 respectively. The
photos showing the LRs and LCRs
are presented in Figure 9.4 to Figure 9.7 and Figure 9.9 to Figure 9.12 respectively. In terms of the
visual aspect, Visual Sensitive Receivers (VSRs)
within the Zones of Visual Influence (ZVI) of the project are mapped in Figure 9.13. The photos
showing the VSRs are presented in Figure 9.14 to Figure 9.17. The photos showing some of their
representative views to the proposed works are presented in Figure 9.18 and Figure 9.19.
9.6.1.2
In the landscape assessment, the existing and planned
landscape resources and character of the assessment areas would be described,
appraised, analyzed and evaluated. Plans of suitable scale showing the
baseline landscape resources and landscape character mapping of impact assessment
are used to present the findings of impact assessment. A broad brush tree
survey which identifies the species and approximate numbers to be affected is
included. The assessment focuses on the sensitivity of the landscape
framework and its ability to accommodate change. The degree of
compatibility of the Project and associated works with the existing and planned
landscape settings would be identified. The landscape impact assessment
quantifies the potential landscape impacts as far as possible, so as to
illustrate the significance of such impacts arising from the Project and
associated works. All landscape impacts are clearly mapped.
9.6.1.3
In the visual impact assessment, clear illustrations
including mapping of visual impact would be provided. The assessment
includes:
l
Identification and plotting of visual envelope of the
Project and associated works,
l
Identification of key groups of sensitive receivers
within the visual envelope with regard to views from ground level, sea level
and elevated vantage points,
l
Description of the visual compatibility of the Project
and associated works within the surrounding, both existing and planned uses,
its obstruction and interference with the key views of the adjacent areas, and
l
Description of severity of visual impacts in terms of
nature, distance and number of sensitive receivers. The visual impact of
the Project and associated works with and without mitigations shall be
assessed, and the effectiveness of the mitigation measures shall be
demonstrated.
9.6.1.4
The merits of preservation in totality, in parts or
total destruction of existing landscape and the establishment of new landscape
character areas are evaluated. Alternative alignment(s), design(s) and
construction methods that would avoid or reduce the identified landscape and
visual impacts have been evaluated for comparison before adopting other
mitigation or compensatory measures to alleviate the impacts. The mitigation
measures proposed would not only be concerned with damage reduction but also
include consideration of potential enhancement of existing landscape and visual
quality.
9.6.1.5
Measures would be included in the detailed design, construction
and operation of the Project and associated works to mitigate landscape and
visual impact and reduce them to the acceptable levels. Relevant
responsible parties would be identified for the on-going management and
maintenance of the proposed mitigation works to ensure their effectiveness
throughout the operation phase of the Project and associated works. A
practical programme and funding proposal for the
implementation of the recommended mitigation measures would be provided.
9.7
Review of Planning and Development Control
Framework
9.7.1.1
A review of the existing and planned development
framework for the proposed works and for the surroundings has been
considered. It aims to identify issues for the neighbouring
planned land uses, to identify potential resources and sensitive receivers, and
to ensure a high compatibility between the proposed project and the
surroundings.
9.7.1.2
The following Outline Zoning Plans (OZP) have been
reviewed: Sheung Pak Nai
& Ha Pak Nai Outline Zoning Plan OZP no.
S/YL-PN/9; Ping Shan OZP no. S/YL-PS/11; Lam Tei
& Yick Yuen OZP no. S/TM-LTYY/6 and Tuen Mun OZP No. S/TM/23.
However, the project site and areas within the 500m study boundary are not covered
within any OZP and no land use is specified in the statutory plans.
9.7.1.3
The proposed STF is considered to be compatible with
the adjacent environment. Landscape and Visual Mitigation Measures will be
applied to avoid the adverse landscape and visual impacts in consideration with
the surrounding environment.
9.8
Landscape Resources
9.8.1.1
Although situated in a remote location, the area is
strongly influenced by human disturbance in terms of landscape resource
pattern. Landscape resources are identified and described below.
LR1 – Ash-lagoon and
Seashore
9.8.1.2
The ash-lagoon itself is considered as a unique
landscape resource. It has been formed to be a dump site - a temporary
storage site for ash generated from the adjacent power plant. Throughout
the years, a number of grasses, creepers, groundcovers, and small shrubs have
grown. Larger shrubs and even small trees, such as Macaranga
tanarius and Leucaena
leucocephala, are even found at the edge of the
lagoon, including along the seawalls. Some portions have become somewhat
marshy with grasses and water ponds (or water-like liquid ponds). The
force of nature is evident, especially for the Middle Lagoon where active
dumping has mostly ceased for years. Several bird species have also been
spotted, and reference should be made to Section 7 of this EIA.
LR2 – Tidal Stream
9.8.1.3
This LR refers to two semi-natural to manmade water
channels found within the study boundary. These water channels may be
formed during the construction and may result in significant establishment of
shrubby riparian vegetation with occasional trees, along some of the stream
banks.
LR3 – Young Mangrove
9.8.1.4
This LR refers to small mangroves found at certain
locations of the tidal streams where sediments have accumulated. There is
a mix of small mangrove trees and grasses/ creepers, suggesting an early,
unstable stage of mangrove colonization.
LR4 – Disturbed Woodland
9.8.1.5
This LR refers to disturbed woodland, located in and
between various abandoned village areas and hard-paved platform areas.
Most tree species are common in this area, including Celtis
sinensis, Leucaena leucocephala, Ligustrum sinense, Macaranga tanarius, Microcos paniculatus, Rhus spp, and Sterculia lanceolata. Several large and mature trees
including Ficus microcarpa,
Clausena lansium and Dimocarpus longan are found
planted at several locations where village houses once existed. An area
along the access road to the abandoned village site is dominated mostly by Hibiscus
tiliaceus, which may suggest the original
shoreline before the ash-lagoon was constructed.
LR5 – Grassland/ Shrubland
9.8.1.6
This LR refers to the barren hillside areas or
disturbed areas dominated by mostly grasses and groundcovers with some small
shrubs. There are occasional small trees, limited to pioneer trees such
as Macaranga tanarius
and Leucaena leucocephala.
LR6 – Slope/ Reinstated
Plantation
9.8.1.7
This LR refers to manmade slopes or disturbed flat
areas planted or reinstated with hydroseeding and
woodland mix, comprised of a mix of planted and self-seeded trees. These
trees are of common native and exotic species, including Acacia spp., Casuarina equisetifolia, Celtis sinensis, Eucalyptus spp.,
Ficus spp., and Macaranga tanarius etc.
LR7 – Seawater
9.8.1.8
This LR refers to the sea area adjacent to the site.
9.9
Landscape Character Areas
9.9.1.1
The area is remote with very few people, except truck
drivers and workers in the ash-lagoon and WENT landfill site. Access to
many LCAs is either restricted by guards or hidden by
topography and vegetation. Landscape character is widely diversified, and
in fact, quite contrasting within the study boundary. LCAs
have been identified and are described below.
LCA1 –‘Man-made’Ash-lagoon and Seashore
9.9.1.2
This LCA refers to the ash-lagoon and the manmade rocky
seawall, which covers a large, open area. It is isolated from the
surroundings by distance, vegetation and water, with a distant view to the
hills at the south and the sea to the north. The ash-lagoon is not open
to the public and access is restricted by guards at the entrance.
Depending on the ‘age’ of different phases of the ash-lagoon, the site is
mostly covered with exposed ash, liquids or semi-liquids, medium-tall grasses,
small shrubs and creepers. There are also occasional birds resting in the
area. The LCA feels secluded and somewhat like a sanctuary, creating a
strong contrast to LCA2 and LCA3. However, due to restricted access and
its nature as a dump site or wasteland, its sensitivity is only Medium, not
High.
LCA2 – Unpleasant Landfill
Site
9.9.1.3
This LCA refers to the adjacent WENT landfill site,
which is characterized by heavy trucks, dust, smells, and landfill/ industrial
nature. The area is unpleasant, and access is restricted at the entrance.
LCA3 – Dusty Road
9.9.1.4
This LCA refers to Nim Wan
Road and the surrounding hilly and/ or vegetated landscape. Nim Wan Road is the only access road to the ash-lagoon and
WENT landfill site. Although trees are found along the road, this section
of Nim Wan Road within the study boundary is
characterized by heavy trucks, dust, and smells, with very few other types of
vehicles and pedestrians. Views along the road are restricted by topography
and vegetation. The space is unpleasant to be inside.
LCA4 – Abandoned Area
9.9.1.5
This LCA refers to the abandoned village area to the
south of the ash-lagoon. The village was a small seaside village before the
ash-lagoon was built, as evident by an old Tin-hau
temple and some building rubble remaining in the area. There are also
some large, abandoned, hard-paved platforms, which were later found to be the
ex-BBC station during desktop study. Very few people know of the village
and access to the area nowadays, as the area is somewhat hidden by dense
vegetation with only one access road of gravel and dirt.
LCA5 – Barren Hillside
9.9.1.6
This LCA refers to the hillside area and the firing range
to the south of the ash-lagoon. The landscape is characterized by exposed
rocks and low grasses with occasional shrubs and small trees. Due to
steep topography and its proximity to the firing range, few people would like
to go to the area.
9.10
Landscape Sensitivity to Change
9.10.1.1
The landscape resources and landscape character areas
that would be potentially affected during the construction phase and operation
phase, together with their sensitivity to change, are listed in Table 9.2.
Table 9.2
List of the Landscape Resources and Landscape Character Area and its
Sensitivity to Change
Id.
No.
|
Landscape
Resource/Character
Area
|
Major
Tree Species
(Common,
Rare)
|
Tree
Size
(Large,
Medium,
Small)
|
Amenity
value of the trees
(Low,
Medium, High)
|
Sensitivity
to Change
(Low, Medium,
High)
|
LR1
|
Ash-lagoon and
Seashore
|
Common
|
Medium
|
Medium
|
Medium
|
LR2
|
Tidal Stream
|
Common
|
Small
|
High
|
High
|
LR3
|
Young Mangrove
|
Common
|
Small
|
High
|
High
|
LR4
|
Disturbed Woodland
|
Common
|
Medium
|
Medium
|
Medium
|
LR5
|
Grassland/ Shrubland
|
Common
|
Small
|
Low
|
Low
|
LR6
|
Slope/ Reinstated Plantation
|
Common
|
Small
|
Low
|
Low
|
LR7
|
Seawater
|
Nil
|
Nil
|
Nil
|
Low
|
LCA1
|
‘Man-made’ Ash-lagoon and Seashore
|
Common
|
Medium
|
Medium
|
Medium
|
LCA2
|
Unpleasant Landfill Site
|
Common
|
Small
|
Low
|
Low
|
LCA3
|
Dusty Road
|
Common
|
Small
|
Low
|
Low
|
LCA4
|
Abandoned Area
|
Common
|
Medium
|
Medium
|
Medium
|
LCA5
|
Barren Hillside
|
Common
|
Small
|
Low
|
Low
|
9.11
Tree Survey Results
9.11.1.1
A broad brush tree survey, which identifies the species
and approximate numbers to be affected, was conduced. The survey area
includes the site area of the STF and its vicinity.
9.11.1.2
A total of 1,184 nos. of trees, which are in a trunk
diameter of 95mm or more and a height of 1.3m above
the ground level as defined in ETWB TCW No. 3/2006, was identified within the
survey area. Approximately 460 trees would be affected due to the
construction works of the STF. Most affected species identified in the
ash-lagoon and seashore (LR1 and LCA1) are common trees, such as Casuarina equisetifolia
(5%), Celtis sinensis
(4%), Leucaena leucocephala
(1%), Macaranga tanarius
(84%) and Acacia confuse (6 %). Among the affected trees,
approximate 5 nos. are weed trees “Leucaena leucocephala”. No LCSD Champion Trees or Registered Old
and Valuable Trees are found. The heights of the trees are in a range of 1.5m
to 12m; their trunk diameters are ranging from 85mm to 480mm; and their spreads
are from 1m to 7m. It was found that about
2% of the trees were in poor health condition and 98% of the trees were in fair
health condition; 7% of the trees were in poor form and 93% of the trees were
in fair form; 7% of the trees were with low amenity value and 93% of the trees
were with medium amenity; 99% of the trees were with low survival rate after
transplanting and 1% of the trees were with medium survival rate after
transplanting.
9.12
Zone of Visual Influence (ZVI)
9.12.1.1
The primary and secondary ZVI for the Project during
the construction phase are illustrated in Figure 9.13. The photos of
the Visual Sensitive Receivers (VSRs) within the
Study Area and the views from the VSRs are
illustrated in Figure 9.14 to Figure 9.19. Primary ZVI is the
area within 1000m from the proposed developments while secondary ZVI is the
area with an average distance of more than 1000m from the developments.
9.13
Visual Sensitive Receivers (VSRs)
9.13.1.1
Due to the remoteness of the site, only a few VSRs were identified. Table 9.3 lists the VSRs found within the ZVIs. For
ease of reference, each VSR is given an identity number, which is used in all
relevant tables and figures in this report. VSR are divided into 6 types:
Commercial, Commercial/ Residential, Residential, Recreational, Government/
Institution/ Community / Occupational and Transport related.
9.13.1.2
“Frequency of View” depends on the type and nature of VSRs: all Residential VSRs and
Commercial/ Residential VSRs are frequent; all other
commercial VSRs are occasional; for Government/
Institution/ Community VSRs, institution-related,
post-office-related VSRs and those with ‘Glimpse
Degree of Visibility’ are rare, all other Government/ Institution/ Community VSRs are occasional; all Recreational VSRs
within the waterfront are very frequent, those with ‘glimpse Degree of
Visibility’ are rare, the others are occasional; transport related VSRs depends on ‘Minimum Distance between VSRs and Impact Source’ and ‘Degree of Visibility’,
9.13.1.3
“Sensitivity to Change” are high for VSRs with medium to many ‘Number of Individuals’, good
‘Quality of Existing View’, 0-200 m ‘Minimum
Distance between VSRs and Impact Source’, partial to
full ‘Degree of Visibility’ and occasional to very frequent ‘Frequency of
View’; “Sensitivity to Change” are low for VSRs with
glimpse ‘Degree of Visibility’, more than 950m ‘Minimum Distance between VSRs and Impact Source’, or rare ‘Frequency of View’;
otherwise “Sensitivity to Change” are Medium. The sensitivity of change of the VSRs is provided in Table 9.3.
9.13.1.4
The magnitude of the impacts, before implementation of
mitigation measures, on the landscape resources and character areas that would
occur in the construction phase are described and tabulated in Table 9.4.
9.13.1.5
Most of the VSRs are
insensitive and with few population. The views of the VSRs
to the surroundings are often blocked by vegetation and topography, except for
those having the coastal view of the STF.
Table 9.3 Visual Sensitive Receivers (VSRs) and their Sensitivity to Change
Id. No.
|
Key Visual Sensitive Receivers (VSRs)
|
Type of VSRs
|
Number of Individuals
(Many/ Medium/ Few/ Very Few)
|
Quality of Existing View
(Good/ Fair/ Poor)
|
Availability of
Alternative Views
(Yes/ No)
|
Degree of Visibility
(Full/ Partial/
Glimpse)
|
Frequency of View
(Very Frequent/ Frequent/
Occasional/ Rare)
|
Sensitivity to Change
(Low, Medium, High)
|
Construction
|
Operation
|
VSR1
|
Shekou
|
Residential
|
Many
|
Poor
|
Yes
|
Glimpse
|
Occasional
|
Medium
|
Medium
|
VSR2
|
Pak Nai
|
Residential/
tourist
|
Medium
|
Good
|
Yes
|
Partial
|
Occasional
|
High
|
High
|
VSR3
|
Sea of Deep Bay
|
Sea Travelers
|
Few
|
Good
|
Yes
|
Glimpse
|
Occasional
|
Low
|
Low
|
VSR4
|
HKSZ Western Corridor
|
Residential
|
Many
|
Good
|
Yes
|
Glimpse
|
Rare
|
Low
|
Low
|
VSR5
|
WENT Landfill Site
|
Occupational
|
Very few
|
Good
|
Yes
|
Full
|
Rare
|
Low
|
Low
|
VSR6
|
Ash-lagoon
|
Occupational
|
Few
|
Fair
|
Yes
|
Full
|
Rare
|
Low
|
Low
|
VSR7
|
Power Station
|
Occupational
|
Few
|
Fair
|
Yes
|
Glimpse
|
Rare
|
Low
|
Low
|
VSR8
|
Firing Range
|
Hikers
|
Very few
|
Good
|
Yes
|
Partial
|
Rare
|
Low
|
Low
|
VSR9
|
Nim Wan Road
|
Travelers
|
Few
|
Fair
|
Yes
|
Glimpse
|
Rare
|
Low
|
Low
|
VSR10
|
Future Access Road
|
Travelers
|
Few
|
Fair
|
Yes
|
Partial
|
Occasional
|
Medium
|
Medium
|
R
= Residential; C = Commercial, C/R = Commercial/Residential, GIC =
Government/Institution/Community, O = Open space, OU = Others use; T =
Transport related.
Table 9.4 Visual Sensitive Receivers (VSRs) and Their Magnitude of Impacts
Id No.
|
Key Visual Sensitive
Receiver (VSR)
|
Blockage of View
(Full/ Partial/ Glimpse
|
Viewing Distance
(m)
|
Scale of Development
(Large/ Medium/ Small)
|
Compatibility
(Good/ Fair/ Poor)
|
Duration of Impacts
(Very Frequent/ Frequent/
Occasional/ Rare)
|
Reversibility of Change
(Yes/ No)
|
Magnitude of Impacts
(Large/ Intermediate/ Small/
Negligible
|
Construction
|
Operation
|
VSR1
|
Shekou
|
Glimpse
|
6000
|
Small
|
Fair
|
Rare
|
No
|
Small
|
Small
|
VSR2
|
Pak Nai
|
Partial
|
1500
|
Medium
|
Fair
|
Frequent
|
No
|
Intermediate
|
Intermediate
|
VSR3
|
Sea of Deep Bay
|
Glimpse
|
5000
|
Medium
|
Fair
|
Rare
|
No
|
Small
|
Small
|
VSR4
|
HKSZ Western Corridor
|
Glimpse
|
6500
|
Small
|
Fair
|
Rare
|
No
|
Negligible
|
Negligible
|
VSR5
|
WENT Landfill Site
|
Full
|
500
|
Large
|
Fair
|
Occasional
|
No
|
Small
|
Small
|
VSR6
|
Ash-lagoon
|
Partial
|
1000
|
Medium
|
Fair
|
Occasional
|
No
|
Small
|
Small
|
VSR7
|
Power Station
|
Partial
|
1800
|
Medium
|
Fair
|
Rare
|
No
|
Negligible
|
Negligible
|
VSR8
|
Firing Range
|
Partial
|
1500
|
Medium
|
Fair
|
Rare
|
No
|
Negligible
|
Negligible
|
VSR9
|
Nim Wan Road
|
Glimpse
|
500
|
Large
|
Fair
|
Rare
|
No
|
Small
|
Small
|
VSR10
|
Future Access Road
|
Full
|
5
|
Large
|
Fair
|
Occasional
|
No
|
Intermediate
|
Intermediate
|
R
= Residential; C = Commercial, C/R = Commercial/Residential, GIC =
Government/Institution/Community, O = Open space, OU = Others use; T =
Transport related.
9.14
Landscape Impact Assessment
9.14.1
Sources of Landscape Impacts
Construction Phase
9.14.1.1
Sources of impacts in the construction phase would
include:
·
construction
of administration building & visitor/education centre, wastewater
treatment plant & sewage holding tank, seawater pumping station,
desalination plant & storage tank (2-storey high)
·
chimney
(about 65m above ground with dimensions of 5m × 7.5m)
·
installation
of incinerators (about 30m above ground)
·
installation
of utilities, including water, drainage and power
·
temporary
site access areas, site cabins and heavy machinery
·
stockpiling
of excavated and construction materials
·
increased
road traffic congestion
·
removal
of existing vegetation
·
after-dark
lighting and welding
·
dust
during dry weather
·
decommissioning
of the existing ash lagoon
Operation Phase
9.14.1.2
The sources of impacts of the project in the operation
stage would be related to the following above ground structures:
·
incinerators
and chimney
·
new
administration building, control room and bridge
·
chemical
storage building and chemical dosing area
·
wastewater
treatment plant and sewage holding tank
·
seawater
pumping station, desalination plant and storage tank
9.14.2
Degree of Compatibility of Project
9.14.2.1
The Project would cause change in the existing
landscape setting of the ash-lagoon and seashore area, which is currently a
dump site of ash with shrubland landscape character,
as the existing tree or shrubs in the site area would be affected.
However, it is noted that the affected trees are of low to medium amenity value
and the landscape setting of the surrounding area is unpleasant due to the
existence of the WENT landfill and dusty road.
9.14.3
Nature and Magnitude of Landscape Impacts
9.14.3.1
During the construction phase, the impacts to the
landscape resources and landscape character areas would be negligible, except
for ash-lagoon and seashore (LR1 and LCA1). The magnitude and description of
the impacts on LR1 and LCA1 are provided in Table 9.5.
Table 9.5
Significant Landscape Impacts of the Proposed Works during Construction Phase
Id No.
|
Landscape Resources/
Landscape Character Areas
|
Source of Impact
|
Description of Impacts
|
Magnitude of Impacts
|
LR1
|
Trees on Ash-lagoon and Seashore
|
· Construction works within STF
· Storage of construction equipment and
plant
· Construction traffic
· Material stockpiling
· Night lighting etc.
· Temporary site access area, site cabins
and heavy machinery
|
· Approx.460 no. of existing trees within
the STF would be affected.
· Amenity value of affected trees are
medium
|
Large
|
LCA1
|
‘Man-made’ Ash-lagoon and Seashore
|
· Construction works within STF and works
areas
· Storage of construction equipment and
plant
· Construction traffic
· Material stockpiling
· Night lighting etc.
· Temporary site access area, site cabins
and heavy machinery
|
· Approx. 460 no. of existing trees within
the STF and works area would be affected.
· Amenity value of affected trees are
medium
|
Large
|
9.14.3.2
As some impacts during the construction phase would be
permanent and irreversible, the magnitude of the impact to the ash-lagoon and
seashore (LR1 and LCA1) during the operation phase would the same as that
during the construction phase.
9.14.4
Prediction of Significance of Landscape Impacts
9.14.4.1
The potential significance of the landscape impacts
during the construction and operation phases before the implementation of the
mitigation measures are provided in Table 9.8. The impact
significance of most landscape resources and landscape character areas would be
insubstantial, except for ash-lagoon and seashore (LR1 and LCA1).
9.14.5
Landscape Mitigation Measures
9.14.5.1
The proposed landscape mitigation measures, together
with an indication of funding, implementation and maintenance agencies, in the
construction and operation are listed in Table 9.6 and Table 9.7.
Generally, all landscape mitigation measures are to be implemented as early as
possible and they are illustrated in Figure 9.20 to Figure 9.23.
9.14.5.2
Aesthetic design of proposed structure will be
sensitive design to match with adjacent landscape setting of the site. Greening
is proposed along the boundary to provide further screening and enhance the
waterfront area.
9.14.5.3
Considering trees with trunk diameter measures 95 mm or
more and neither under an unrecoverable health problem nor poor condition,
there are about 460 no. of trees would be affected by the Project. It is
proposed to remove the five weed trees “Leucaena
leucocephala”. Those affected trees with
medium survival rate after transplanting would be transplanted. For the
remaining affected trees with low survival rate after transplanting are
proposed to be felled. Implementation of compensatory planting for heavy
standard trees will be of a ratio not less than 1:1 within the site. Detailed
tree preservation, transplanting and felling including compensatory planting
proposals will be prepared and submitted to relevant government departments for
approval in accordance with ETWB TC no. 3/2006 and ETWB TCW No. 29/2004.
9.14.5.4
It is expected that the heavy standard trees would
create immediate greening effect. As the affected trees, which are of low
to medium amenity value, would be replaced by heavy standard trees, the
proposed mitigation measures would not only alleviate the impact due to the
project, but also enhance the existing landscape.
Table 9.6
Proposed Landscape and Visual Mitigation Measures for Construction Phase
ID No.
|
Landscape and Visual Mitigation Measures
|
Funding
Agency
|
Implementation
Agency
|
Maintenance/
Management Agency
|
CM1
|
Topsoil,
where identified, should be stripped and stored for re-use in the
construction of the soft landscape works, where practical.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
CM2
|
Existing
trees to be retained on site should be carefully protected during
construction.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
CM3
|
Trees
unavoidably affected by the works should be transplanted where practical.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
CM4
|
Compensatory
tree planting should be provided to compensate for felled trees.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
CM5
|
Control
of night-time lighting.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
CM6
|
Erection
of decorative screen hoarding compatible with the surrounding setting.
|
EPD
|
EPD (via Contractor)
|
EPD (via Contractor)
|
Table 9.7
Proposed Landscape and Visual Mitigation Measures for Operation Phase
ID No.
|
Landscape and Visual Mitigation Measures
|
Funding Agency
|
Implementation Agency
|
Maintenance/ Management Agency
|
OM1
|
Aesthetic
design of the façade, chimneys of STF and associated structures to harmonize
with the surrounding settings.
|
EPD
|
EPD (via
Contractor)
|
EPD (via
Contractor)
|
OM2
|
Shrub
and climbing planting to soften proposed structures
|
EPD
|
EPD (via
Contractor)
|
EPD (via
Contractor)
|
OM3
|
Heavy standard tree planting to screen proposed
associated structures.
|
EPD
|
EPD (via
Contractor)
|
EPD (via
Contractor)
|
OM4
|
Reinstated of disturbed area
|
EPD
|
EPD (via
Contractor)
|
EPD (via
Contractor)
|
9.14.6
Programme of Implementation of Mitigation Measures
9.14.6.1
The construction phase mitigation measures listed above
shall be adopted from the commencement of construction and shall be in place
throughout the entire construction period. The operation phase mitigation
measures listed above shall be adopted during the detailed design and be built
as part of the construction works so that they are in place at the date of
commissioning of the Project.
9.14.7
Residual Landscape Impacts
9.14.7.1
The potential significance of landscape impacts during
the construction and operation phases after the implementation of the
mitigation measures are provided in Table 9.8. The assessment was
conducted based on the assumptions that the recommended mitigation measures
would be implemented, and the full effect of the mitigation measures would be
realized after 10 years.
9.14.7.2
After the implementation of the mitigation measures,
the impact significance of the STF to the ash-lagoon and seashore during the
construction phase and on day 1 of the operation phase would be reduced to
moderate, and the impact significance after 10-year operation of the STF would
be slight.
9.14.7.3
Considering the facts that the affected trees with low
to medium amenity value will be compensated by high standard trees, and
landscape value of the existing “man-made” ash-lagoon, which is a dump site of
ash with shrubland landscape character, is not high,
the impact during the construction and operation phase are considered
acceptable.
Table 9.8 Significance of Landscape Impacts in the
Construction and Operation Phases
Id.
No.
|
Landscape Resource /
Landscape Character
|
Sensitivity
to Change
(Low,
Medium, High)
|
Magnitude
of Change (Negligible, Small, Intermediate, Large)
|
Impact
Significance before Mitigation
(Insubstantial,
Slight, Moderate, Substantial)
|
Recommended Mitigation
Measures
|
Impact
Significance Day 1 after Mitigation
|
Impact Significance 10 years after Mitigation
|
(Insubstantial,
Slight, Moderate, Substantial)
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Operation
|
LR1
|
Ash-lagoon and Seashore
|
Medium
|
Medium
|
Large
|
Large
|
Substantial
|
Substantial
|
CM1 to CM4,
OM1 to OM4
|
Moderate
|
Moderate
|
Slight
|
LR2
|
Tidal Stream
|
High
|
High
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR3
|
Young Mangrove
|
High
|
High
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR4
|
Disturbed Woodland
|
Medium
|
Medium
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR5
|
Grassland/ Shrubland
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR6
|
Slope/ Reinstated Plantation
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LR7
|
Seawater
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA1
|
‘Man-made’ Ash-lagoon and Seashore
|
Medium
|
Medium
|
Large
|
Large
|
Substantial
|
Substantial
|
CM2
to CM4,
OM1 to OM4
|
Moderate
|
Moderate
|
Slight
|
LCA2
|
Unpleasant Landfill Site
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA3
|
Dusty Road
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA4
|
Abandoned Area
|
Medium
|
Medium
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
LCA5
|
Barren Hillside
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Nil
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
9.15
Visual Impact
Assessment
9.15.1
Potential Sources of Visual Impacts
9.15.1.1
The Project would create varying levels of visual
impact during the construction and operation phases. The potential
sources of impacts are stated in Section 9.14.1.
9.15.2
Prediction of Significance of Visual Impacts
9.15.2.1
The potential significance of the visual impacts during
the construction and operation phases without the mitigation measures are
provided in Table 9.9. The photomontages of the STF before the
implementation of mitigation measures are illustrated in Figure 9.22 and Figure 9.23. The significance
of the visual impacts to the residents in Shekou
(VSR1) and the travelers of the future access road (VSR10), which would be
opened in year 2016/17, would be moderate, while that to the residents in Pak Nai would be substantial (VSR2).
9.15.3
Visual Mitigation Measures
9.15.3.1
The proposed visual mitigation measures, together with
an indication of funding, implementation, and management and maintenance
agencies, in the construction and operation phases are summarized in Table
9.6 and Table 9.7. The visual mitigation measures are illustrated in
Figure 9.22 and Figure 9.23.
9.15.3.2
The project areas are predominantly in waterfront
context and surrounding by industrial waste land, bounded by dense vegetations
and mountain at the back drop. Therefore mitigation measures would focus on
enhancing the visual quality and compatibility of the STF’s
waterfront settings. Architectural design theme with respect the overall
image/development to achieve visual conformity will be developed in details
during the detailed design stage. The facade colour
theme, pattern, texture, materials, finishing, greening of the structures and
building mass will be sensitively designed in form, base colour/tone
variation, micro and macro texture, and reflectivity/ light absorbance to avoid
glare and to match with adjoining environment.
9.15.3.3
The programme of
implementation of the mitigation measures is as listed in Section 9.14.6.
9.15.4
Residual Visual Impacts
9.15.4.1
The residual visual impacts in the construction and
operation phases after the implementation of proposed mitigation measures are
listed out in Table 9.9. It was assumed that the recommended
mitigation measures would be implemented, and the full effect of the mitigation
measures would be realized after 10 years.
9.15.4.2
After the implementation of the mitigation measures,
the residual impacts during the construction phase and on day 1 of the
operation phase to the residents in Shekou (VSR1) and
in Pak Nai (VSR2), and the travelers of the future
access road (VSR10) would be reduced to slight or moderate. After 10-year
operation of the STF, the residual impact to these VSRs
would be reduced to insubstantial or slight.
Table 9.9
Significance of Visual Impacts in Construction and Operation Phases
Id
No
|
Key Visual Sensitive Receivers (VSRs)
|
Receptor
Sensitivity
(Low, Medium,
High)
|
Magnitude
of Impact
(Negligible,
Small, Intermediate, Large)
|
Impact
Significance without Mitigation Measures
(Insubstantial,
Slight, Moderate, Substantial)
|
Recommended
Mitigation Measures
|
Residual
Impact Significance with Mitigations
(Insubstantial,
Slight, Moderate, Substantial)
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Day
1
|
Year
10
|
VSR1
|
Shekou
|
Medium
|
Medium
|
Small
|
Small
|
Moderate
|
Moderate
|
CM5 to CM6,
OM1 to OM4
|
Slight
|
Slight
|
Insubstantial
|
VSR2
|
Pak Nai
|
High
|
High
|
Intermediate
|
Intermediate
|
Substantial
|
Substantial
|
Moderate
|
Moderate
|
Slight
|
VSR3
|
Sea of Deep Bay
|
Low
|
Low
|
Small
|
Small
|
Slight
|
Slight
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR4
|
HKSZ Western Corridor
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR5
|
WENT Landfill Site
|
Low
|
Low
|
Small
|
Small
|
Slight
|
Slight
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR6
|
Ash-lagoon
|
Low
|
Low
|
Small
|
Small
|
Slight
|
Slight
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR7
|
Power Station
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR8
|
Firing Range
|
Low
|
Low
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR9
|
Nim Wan Road
|
Low
|
Low
|
Small
|
Small
|
Slight
|
Slight
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
VSR10
|
Future Access Road
|
Medium
|
Medium
|
Intermediate
|
Intermediate
|
Moderate
|
Moderate
|
Slight
|
Slight
|
Insubstantial
|
9.16
Conclusion
9.16.1.1
Seven landscape resources and five landscape character
areas were identified within 500m from the site area. The impact to these
landscape resources and landscape character areas would be insubstantial,
except for the ash-lagoon and seashore (LR1 and LCA1). Mitigation
measures, such as aesthetic design of the proposed STF matching with adjacent
landscape setting of the site, greening along the site boundary to provide
screening and enhance the waterfront area, would be implemented. After
the implementation of the mitigation measures, the residual impact to the
ash-lagoon and seashore during the construction phase and on day 1 of the
operation phase would be reduced to moderate, and the long-term residual impact
to the ash-lagoon and seashore would be reduced to slight. Considering
the fact that the affected trees in the site area are of low to medium amenity
value and landscape value of the existing “man-made” ash-lagoon is not high,
the impact during the construction and operation phase are considered
acceptable.
9.16.1.2
Ten visual sensitive receivers (VSRs)
were identified within the zone of visual influence. Most of these VSRs have low sensitivity to change, and the magnitude of
impact to them would be negligible or small. Therefore, the visual impact
to seven VSRs would be insubstantial or slight during
construction and operation phase. However, the visual impact to the
residents in Shekou (VSR1) and the travelers of the
future access road adjacent to the STF (VSR10) would be moderate, while that to
the residents in Pak Nai would be substantial
(VSR2). Mitigation measures would be implemented during the construction
and operation phase to reduce the potential visual impacts to these VSRs. After the implementation of the mitigation
measures, the residual impact to these VSRs during
the construction phase and on day 1 of the operation phase would be reduced to
slight or moderate, and the long-term residual impact to these VSRs would be reduced to insubstantial or slight.
9.16.1.3
Overall, it is considered that the residual landscape
and visual impacts of the proposed development would be acceptable with
mitigation measures during construction and operation phases.